Audrey Posten, Times-Register
The McGregor Council, at its June 17 meeting, approved the plans, specifications, opinion of cost and form of contract for the upcoming Sixth Street Bridge Project.
Tim Cutsforth, senior project manager with HR Green, said work will include taking out the bridge, which crosses the city’s storm sewer, and replacing it with a box culvert.